Portfolio

The Festival Companies

  • Location

    240 Post Street, San Francisco, CA
  • Architect

    WZ Architecture
  • Duration

    7 Months
  • Size

    32,000 sf

Fisher Development performed selective demolition of this four-story retail space in an occupied building on Union Square. Scope included seismic strengthening, installing three sets of escalators, new MEPs and a new wood frame mezzanine infill. Site logistics were a major factor as much of the work had to be performed at night and at off-peak hours.